Risk Management Analysis in Container Yard Development Projects in Eastern Indonesia

##plugins.themes.academic_pro.article.main##

Prafajar Suksessanno Muttaqin
* Corresponding author: prafajars@telkomuniversity.ac.id
Nia Novitasari
Erlangga Bayu Setyawan

Abstract

A container yard is a place for storing containers, a place for cleaning, and repairs, as well as a place for carrying out container surveys. Currently planning the construction of a container yard in Eastern Indonesia is being carried out. In its construction, a container yard requires large investment costs due to many factors such as the difficulty and high cost of transporting raw materials, permits that require planning, to the need for proper business processes in order to provide smooth operational activities by minimizing risk. The purpose of this study is to identify the risks and causes of risks involved in the container depot development project in Eastern Indonesia using the quantitative risk assessment (QRA) method, so as to provide the most influential risk management recommendations. The research succeeded in identifying 24 risks and 24 causes of risk. Furthermore, from the calculation results, it was concluded that there were 9 most influential risks. 


Depo kontainer merupakan tempat penyimpanan kontainer, tempat pembersihan, perbaikan, serta tempat untuk pelaksanaan survei kontainer. Saat ini sedang dilakukan perencanaan pembangunan depo kontainer di Indonesia Timur. Dalam pembangunanya, depo kontainer membutuhkan biaya investasi yang besar yang disebabkan banyak faktor seperti sulit dan tingginya biaya transportasi bahan baku, perizinan yang membutuhkan perencanaan, hingga kebutuhan akan adanya proses bisnis yang tepat agar dapat memberikan kelancaran pada aktivitas operasional dengan meminimasi risiko. Tujuan penelitian ini adalah mengindenfitikasi risiko dan penyebab risiko yang terdapat pada proyek pembangunan depo kontainer di Indonesia Timur dengan metode quantitative risk assessment (QRA), sehingga dapat memberikan usulan penanganan risiko yang paling berpengaruh. Penelitian berhasil mengidentifikasi 24 risiko dan 24 penyebab risiko. Lebih lanjut dari hasil perhitungan disimpulkan ada 9 risiko paling berpengaruh.

##plugins.themes.academic_pro.article.details##

How to Cite
Muttaqin, P., Novitasari, N., & Setyawan, E. (2023). Risk Management Analysis in Container Yard Development Projects in Eastern Indonesia. MOTIVECTION : Journal of Mechanical, Electrical and Industrial Engineering, 5(1), 173-186. https://doi.org/10.46574/motivection.v5i1.183

References

[1] Herdi Alif Al Hikam, “Kemenhub Sebut 40% Perdagangan Dunia Lewat Laut RI, Dapat Untung?,” https://finance.detik.com/berita-ekonomi-bisnis/d-5144507/kemenhub-sebut-40-perdagangan-dunia-lewat-laut-ri-dapat-untung, 2020.
[2] United Nations, “Review of Maritime Transport,” Geneva, 2021.
[3] Steven W. Hartley and Roger A. Kerin, Marketing: The Core 9TH Edition (International Edition). McGraw Hill, 2021.
[4] P. J. Sobel, D. C. Murdock, J. C. Thomson, and P. K. Miller, “The Institute of Internal Auditors (IIA) Preface COSO Board Members,” 2020.
[5] Darmawi H, Manajemen Risiko Edisi 2, 2nd ed. Jakarta: Bumi Aksara, 2016.
[6] A. Sandyavitri, “Seminar Nasional Teknik Kimia Oleo & Petrokimia Indonesia,” 2008.
[7] F. Moi and I. G. A. N. Purnawirati, “Analisis Manajemen Risiko Pada Proyek Pembangunan Ruas Jalan Baru Waebetu – Tarawaja,” Jurnal Talenta Sipil, vol. 4, no. 1, p. 79, Feb. 2021, doi: 10.33087/talentasipil.v4i1.52.
[8] R. N. Gusti and P. A. Qiguna, “Analisis Risiko Kecelakaan Kerja pada Proyek Pembangunan Gedung Kampus II UINSA Surabaya,” Jurnal Teknik ITS, vol. 2, 2021.
[9] S. S. Shinde and P. M. Rewane, “Risk Assessment of Construction Building Projects And Its Remedies,” International Research Journal of Engineering and Technology, 2020, [Online]. Available: www.irjet.net
[10] V. K. Gupta and J. J. Thakkar, “A quantitative risk assessment methodology for construction project,” Sādhanā, vol. 43, no. 7, p. 116, 2018, doi: 10.1007/s12046-018-0846-6.
[11] M. Nabawy and L. M. Khodeir, “A systematic review of quantitative risk analysis in construction of mega projects,” Ain Shams Engineering Journal, vol. 11, no. 4, pp. 1403–1410, 2020, doi: https://doi.org/10.1016/j.asej.2020.02.006.
[12] Amir MS, Strategi Pemasaran Ekspor, 1st ed. Jakarta: PT. Pustaka Binaman Pressindo, 2000.
[13] “3rd Edition The Australian And New Zealand Standard on Risk Management.,” Australia.