Analysis of Productivity and Annual Cost of Casting Plates and Beams Using Concrete Pump and Columns with Concrete Bucket (Case Study of Residence Apartment Project)

##plugins.themes.academic_pro.article.main##

Irma Wirantina Kustanrika
* Corresponding author: irmawirantina@itpln.ac.id
Wawan Purwanto
Muhammad Sofyan
Yetti Anita Sari
Asri Wahyuningtias

Abstract

Traditional casting in multi-storey buildings necessitates specialized equipment such as concrete buckets and concrete pumps for the application of ready mix concrete. Various types of equipment have an impact on both productivity and the duration of casting. This study collected primary data by conducting field observations at the B Residence Apartment Project, with a specific focus on worker and equipment needs, tool effectiveness, and labor force. The secondary data comprised of structural photos and cost information pertaining to manpower and equipment. The study revealed that the utilization of a concrete pump incurs a cost of IDR 1,231,543 m³, but employing a concrete bucket results in a cost of IDR 1,719,141 m³. The concrete pump achieved a volume of 281.02 m³ in a duration of 1101 minutes, while the bucket achieved a volume of 47.98 m³ in a duration of 538.77 minutes. The productivity of the concrete pump was 0.255 m³/minute, whereas the productivity of the concrete bucket was 0.089 m³/minute. According to these findings, utilizing the concrete pump will greatly enhance time efficiency and decrease the incurred expenses.

##plugins.themes.academic_pro.article.details##

How to Cite
Kustanrika, I., Purwanto, W., Sofyan, M., Sari, Y., & Wahyuningtias, A. (2024). Analysis of Productivity and Annual Cost of Casting Plates and Beams Using Concrete Pump and Columns with Concrete Bucket (Case Study of Residence Apartment Project). MOTIVECTION : Journal of Mechanical, Electrical and Industrial Engineering, 6(3), 249-258. https://doi.org/10.46574/motivection.v6i3.287

References

[1] Muhyiddin, “Covid-19, New Normal, dan Perencanaan Pembangunan di Indonesia [Covid-19, New Normal, and Development Planning in Indonesia],” J. Perenc. Pembang. Indones. J. Dev. Plan., vol. 4, no. 2, pp. 240–252, 2020.
[2] X. R. Wang, E. C. M. Hui, and J. X. Sun, “Population migration, urbanization and housing prices: Evidence from the cities in China,” Habitat Int., vol. 66, pp. 49–56, 2017, doi: 10.1016/j.habitatint.2017.05.010.
[3] C. H. Mulder, “The relationship between population and housing,” Sixty-ninth Sess. UNECE Comm. Hous. L. Manag., pp. 1–12, 2006, [Online]. Available: https://pdfs.semanticscholar.org/897f/7c0f24e14995e7155973c3ba27279d38ecf9.pdf.
[4] J. K. Bedi, R. A. Rahman, and Z. Din, “Heavy Machinery Operators: Necessary Competencies to Reduce Construction Accidents,” IOP Conf. Ser. Earth Environ. Sci., vol. 641, no. 1, pp. 1–11, 2021, doi: 10.1088/1755-1315/641/1/012007.
[5] R. A. Khan, “Role of Construction Sector in Economic Growth: Empirical Evidence from Nigeria,” First Int. Conf. Constr. Dev. Ctries., vol. 7, no. 1, pp. 279–290, 2008, doi: 10.4314/fje.v7i1.4.
[6] Y. Patrisia and R. Coenraad, “Mathematic Modelling of Concrete Pimp Productivity on the Concrete Work of Construction Project in Palangka Raya,” J. Pendidik. Teknol. dan Kejuru. BALANGA, vol. 2, no. 2, pp. 12–22, 2014.
[7] H. A. Rani, Manajemen Proyek Konstruksi. Banda Aceh: CV BUDI UTAMA, 2016.
[8] R. L. Mulatief, K. R. Ratnayanti, and R. Firdaus, “Perbandingan Waktu Dan Biaya Concrete Pump Dan Concrete Bucket Pada Proyek Gedung Telkom University Landmark Tower,” Reka Racana, vol. x, no. xx, pp. 1–13, 2021.
[9] F. Baskara, “Analisis Biaya Dan Waktu Pelaksanaan Pekerjaan Pengecoran Menggunakan Concrete Pump Dan Concrete Bucket (Studi Kasus: Proyek Pembangunan Lanjutan Gedung Perkuliahan S1 Fmipa Ugm),” Sinta, pp. 1–58, 2022.
[10] A. Deni Sujanadi, A. Isya, and Suparjo, “PRODUKTIVITAS PENGECORAN BETON READY-MIXED DENGAN CONCRETE PUMP DAN TOWER CRANE Productivity of Ready-Mixed Concrete Casting with Concrete Pump and Tower Crane,” Spektrum Sipil, ISSN 1858-4896, vol. 1, no. 1, pp. 13–20, 2017.
[11] S. S. Parag and K. R. Pranay, “Study of Factors Affecting Productivity of Pumped Concrete for Multistory Buildings,” Int. J. Recent Innov. Trends Comput. Commun., vol. 3, no. 12, pp. 6521–6524, 2015.
[12] A. B. Siswanto and A. S. Mukhamad, Manajemen Proyek Pengadaan Jasa Konstruksi Dengan E-Procurement View project International Journal of Civil Engineering and Technology View project, vol. 1, no. June. CV. Pilar Nusantara, 2019.
[13] J. Anditia. S, J. Mara, and L. T. Tangdialla, “Analisis Peralatan Beton Ready Mix Pada Pekerjaan Pengecoran Balok Dan Lantai Proyek Gedung Education Center FISIP UNHAS,” Paulus Civ. Eng. J., vol. 4, no. 2, pp. 280–288, 2022, doi: 10.52722/pcej.v4i2.457.
[14] A. S. Nugroho, “Perbandingan Produktivitas Dan Biaya Pada Pekerjaan Pengecoran Antara Alat Concrete Pump Dan Concrete Bucket,” 2021.
[15] A. Y. Pradana and F. Pulansari, “Analisis Pengukuran Waktu Kerja Dengan Stopwatch Time Study Untuk Meningkatkan Target Produksi Di Pt. Xyz,” Juminten, vol. 2, no. 1, pp. 13–24, 2021, doi: 10.33005/juminten.v2i1.217.